Proposed Projects
Project NameNo. of BeneficiariesTotal Cost Estimate
(Rs. Million)
1. Kundasale - Haragama WSP330,00031,200
2. Kandy - North Pathadumbara WSP470,00051,319
3. Kothmale -Riverside WSP19,2003,345
4. Hasalaka WSP49,3705,719
5. Deltota WSP(Deltota Zone only)9,5611,863
6. Nanuoya WSP16,5002,815
7. Hataraliyadda WSP28,9003,613
8. Poondaluoya WSP19,0002,874
9. Medadumbara/Panvila WSP34,792 10,642 
10. Pupuressa/Atabage WSP52,1916,010
11. Nawalapitiya/Pallegama WSP10,073994
12. Naula new WSP90,163 35,95